A.
INTRODUCTION
Eric K. Solorio
A.1
PERMITTING AGENCIES AUTHORITIES, RESPONSIBILITIES AND
PROCESSES
The California Energy Commission (CEC) and the Bureau of
Land Management (BLM)
have prepared
this joint, detailed analysis and statement known as a Staff
Assessment/Draft Plan Amendment/Draft Environmental
Impact Statement
(SA/DPA/DEIS). The Draft
Plan Amendment pertains to the BLM’s California Desert
Conservation Area Plan of 1980 as Amended. The analysis
and statement are
commonly referred to
as a “joint, environmental document” because the SA/DPA/DEIS
addresses the
requirements of the California Environmental Quality Act (CEQA) and
also the
National Environmental Policy Act (NEPA). CEQA is a statute that requires
state (CEC) and
local agencies to identify the significant environmental impacts of their
actions and to
avoid or mitigate those impacts, if feasible. NEPA requires federal
agencies (BLM) to
integrate environmental values into their decision making processes
by considering
the environmental impacts of their proposed actions and reasonable
alternatives to those
actions.
For clarity, staff emphasizes to the reader that this “joint,
environmental document”, is
being used by the
CEC and also the BLM, in separate and distinctly different licensing,
permitting and or
authorization processes. Overall, both the BLM and the CEC will rely
on the
SA/DPA/DEIS document in very similar ways (i.e. considering the proposed
project’s impacts on
the environment).
Because the BLM and the CEC, respectively, will each rely
upon this document to
comply with different
environmental regulations, there are certain portions of the
document titled “CEQA
purposes only” or “NEPA purposes only” or use other similar
language. The CEQA
only portions are identified for the benefit of the CEC’s
environmental review
process while the NEPA only portions are identified for the benefit
of the BLM’s
environmental review process. The balance of the document is for the
benefit of both
agencies respective, environmental reviews.
The authors of this SA/DPA/DEIS are CEC staff, hereafter
referred to as “staff”. Prior to
drafting the joint
document, the BLM and the CEC conducted multiple site visits, in order
to examine the
physical characteristics of the proposed project site. Both agencies also
conducted joint
review of the AFC, POD and related information regarding the proposed
project. The BLM
and the CEC also organized, noticed and held five public meetings
and workshops
to discuss the proposed project. The BLM has also reviewed the
administrative draft of
the SA/DPA/DEIS and provided written comments to the authors
for
incorporation into the SA/DPA/DEIS.
A.1.1
ENERGY COMMISSION’S AUTHORITY AND RESPONSIBILITIES
The Energy Commission has the authority to certify the
construction, modification, and
operation of thermal
electric power plants 50 megawatts (MW) or larger. The Energy
Commission certification is in lieu of any permit
required by state, regional, or local
agencies; and
federal agencies to the extent permitted by federal law (Pub. Resources
Code, § 25500). The Energy
Commission must review thermal power plant Applications
for
Certification (AFC) to assess potential environmental impacts including
potential
impacts to public
health and safety, potential measures to mitigate those impacts, and
compliance with
applicable governmental laws or standards (Pub. Resources Code, §
25519 and § 25523(d)).
The Energy Commission’s siting
regulations require staff to independently review the
AFC and assess whether all of the potential environmental
impacts have been properly
identified, and
whether additional mitigation or other more effective mitigation measures
are necessary,
feasible, and available (Cal. Code Regs., tit. 20, §
1742 and
§ 1742.5(a)).
In addition, staff must assess the completeness and
adequacy of the measures
proposed by the
applicant to ensure compliance with health and safety standards, and
the reliability
of power plant operations (Cal. Code Regs., tit. 20,
§ 1743(b)). Staff is
required to develop
a compliance plan to ensure that applicable laws, ordinances,
regulations, and
standards (LORS) are met (Cal. Code Regs., tit. 20, §
1744(b)).
Staff conducts its environmental analysis in accordance
with the requirements of CEQA.
No additional environmental impact report (EIR) is
required because the Energy
Commission’s site certification program and production of
a Staff Assessment (SA), has
been certified
by the California Resources Agency as meeting all requirements of a
certified regulatory
program (Pub. Resources Code, § 21080.5 and Cal. Code Regs., tit.
14, § 15251 (j)). The Energy
Commission is the CEQA lead agency.
A.1.2.
ENERGY COMMISSION’S SITE CERTIFICATION PROCESS
Upon the Energy Commission receiving a complete
Application for Certification (AFC),
Commission staff begins preparing an SA. The analyses
contained in a SA are based
upon information
from the: 1) AFC, 2) responses to data requests, 3) supplementary
information from local,
state, and federal agencies, interested organizations, and
individuals, 4)
existing documents and publications, 5) independent research, and 6)
comments received at
public workshops. The analyses for most technical areas include
discussions of proposed
conditions of certification. Each proposed condition of
certification is followed
by a proposed means of verification that the condition of
certification has been
met. The SA presents staff’s conclusions about potential
environmental impacts and
conformity with LORS, as well as proposed conditions that
apply to the
design, construction, operation, and closure of the facility.
Upon completion of the SA, it is published and made
available to the applicant,
interveners, public,
agencies and interested parties. Following publication of the SA,
staff provides a
public comment period to resolve issues between the parties and to
narrow the scope
of disputed issues that would likely be presented at evidentiary
hearings held by the
Energy Commission. During the comment period, staff will conduct
additional public workshops
to discuss its conclusions, proposed mitigation, and
proposed
compliance-monitoring requirements. Based on dialogue at the workshops
and written
comments from agencies and the general public, staff may chose to refine
its analysis,
correct minor errors, and or finalize conditions of certification to reflect
areas where
agreements have been reached with the parties. If necessary, staff will
then publish an
Errata to the Staff Assessment which corrects any minor errors in the
SA, elaborates on any details to proposed mitigation
measures and addresses the
comments received.
When producing a joint environmental document, staff will publish
its Errata
simultaneously with and as part of the Final Environmental Impact Statement.
The final document for this review will be titled Staff
Assessment; Errata/Proposed Plan
Amendment/Final Environmental Impact
Statement (SAE/PPA/FEIS).
For the Energy Commission’s purposes in considering the
RSPP, the SAE/PPA/FEIS is
not the
decision document for the Commission’s proceedings nor does it contain
“findings” of the Energy
Commission related to environmental impacts or the project’s
compliance with
local/state/federal legal requirements. The SAE/PPA/FEIS will be
entered into the
evidentiary record and serve as Energy Commission staff’s testimony in
evidentiary hearings to
be held by the Committee of two Commissioners along with a
hearing officer,
who are overseeing this case. The Committee will hold evidentiary
hearings and will
consider all the evidence entered into the record including evidence
presented by staff,
the applicant, all parties, government agencies and public
comments, prior to
proposing its decision. At the public hearings, all parties will be
afforded an
opportunity to present evidence and to rebut the testimony of other parties,
thereby creating a
hearing record on which a decision on the project can be based. The
hearing before the
Committee also allows all parties to argue their positions on disputed
matters, if any,
and it provides a forum for the Committee to receive comments from the
public and other
governmental agencies. It is important to distinguish that the
Commission’s hearing process is completely separate from
the BLM’s process. As
such, evidence
presented at the Commission’s hearings is not evidence, facts or
findings that is
before the BLM.
Following the evidentiary hearings, the Committee’s
recommendation to the full Energy
Commission on whether or not to approve, modify or deny
the proposed project will be
contained in a
document entitled the Presiding Member’s Proposed Decision (PMPD).
Following publication, the PMPD is circulated for 30
days, in order to receive written
public and agency
comments. At the conclusion of the comment period, the Committee
may prepare a
revised PMPD. The final step is presentation of the PMPD by the
hearing officer to
the full Commission for consideration and issuance of an order
granting or denying
of a license to construct and operate the proposed facility.
A.1.3
BUREAU OF LAND MANAGEMENT’S AUTHORITY,
RESPONSIBILITIES,
AND PURPOSE AND NEED
A.1.3.1
Bureau Of Land Management’s Authority and
Responsibilities
Applications to construct and operate commercial solar
energy facilities on public lands,
managed by the BLM,
are processed as right-of-way (ROW) authorizations under Title
V of the Federal Land Policy and Management Act (FLPMA)
of 1976 [43 United States
Code (U.S.C.) 1701 et seq.], and Title 43, Part 2804 of
the Code of Federal Regulations
(CFR).
Applications submitted to the BLM for commercial solar energy development
projects use Form
SF-299. Additional authorities consistent with BLM for processing
such
applications (SF-299), include the following:
• The Energy Policy Act of 2005 (Epact),
which says “It is the sense of Congress that
the Secretary
of the Interior should, before the end of the 10-year period beginning
on the date of
enactment of this Act [August 8, 2005] seek to have approved nonhydropower
renewable
energy projects located on the public lands with a generation
capacity of at least
10,0000 megawatts of electricity.”; and
• Secretarial Order 3285, dated March
11, 2009, which "establishes the development
of renewable
energy as a priority for the Department of the Interior".
In processing the ROW applications and considering taking
related actions to change
land use
designations, the BLM is required under the NEPA to conduct a
comprehensive
environmental review of the proposed project. For the RSPP, this NEPA
review will be
documented in the form of an SA/DPA/DEIS and a subsequent
SAE/PPA/FEIS.
A.1.3.2
BLM Land Use Plan Conformance
The principal land use plan affecting this proposed
project is the U.S. Bureau of Land
Management’s (BLM) California Desert Conservation Area
(CDCA) Plan of 1980, as
amended, and the
West Mojave Desert Management Plan (WEMO), which amends the
CDCA Plan for those specific areas of the Mojave Desert.
In the CDCA Plan, the
location of the
proposed facility includes land that is unclassified and small amount of
classified as
Multiple-Use Class L (Limited Use). The Plan states that solar power
facilities may be
allowed within Limited Use areas after the NEPA requirements are met
by considering
the environmental impacts and reasonable alternatives to the action. The
majority of the
Project is located in unclassified BLM-administered land. The BLM
manages these
parcels on a case-by-case basis.
This DEIS acts as the mechanism for complying with those
NEPA requirements.
Because solar power facilities are an allowable use of
the land as it is classified in the
CDCA Plan, the proposed action does not conflict with the
Plan. However, Chapter 3,
“Energy Production and Utility Corridors Element” of the
Plan states that “Sites
associated with power
generation or transmission not identified in the Plan will be
considered through the
Plan Amendment process.” Because the proposed facility is not
currently identified
within the CDCA Plan, the plan would require an amendment to
authorize the
proposed project.
As specified in Chapter 7, Plan Amendment Process, there
are three categories of Plan
Amendments, including:
• Category 1, for proposed changes that
will not result in significant environmental
impact or analysis
through an Environmental Impact Statement;
• Category 2, for proposed changes that
would require a significant change in the
location or extent
of a multiple-use class designation; and
• Category 3, to accommodate a request
for a specific use or activity that will require
analysis beyond the
Plan Amendment Decision.
Based on these criteria, approval of the proposed project
would require a Category 3
amendment.
The Implementation section of the Energy Production and
Utility Corridors Element of
the CDCA Plan
lists a number of Category 3 amendments that have been approved
since adoption of
the Plan in 1980. An additional amendment is proposed to be added
to this
section of the Plan, and would read “Permission granted to construct solar
energy facility
(proposed Ridgecrest Solar Power Project (RSPP).” a.1.3.3 Bureau of
Land Management’s right-of-way grant
process.
Under federal law, the BLM is responsible for processing
requests for rights-of-way to
construct systems for
generation, transmission, and distribution of electric energy on the
public lands. In
response to Solar Millennium’s application for a ROW grant (CACA
049016) on public land together with a Plan of
Development (POD) to develop the
RSPP, the BLM and CEC generated this SA/DPA/DEIS to
evaluate the potential
environmental impacts of
the proposed action, the No Action alternative, and other
alternative actions
that may meet BLM’s purpose and need. The following outlines the
BLM’s public comment timing and process:
1. The Notice of Availability (NOA) publication in the
Federal Register will begin the
90-day public comment period on the SA/DPA/DEIS
2. Following completion of the comment period, BLM will
review and develop
responses to comments
that were submitted by the public and other agencies. The
responses to the
comments will be incorporated into a joint SAE/PPA/FEIS, which
will also
include identifying the BLM’s preferred project alternative. A Notice of
Availability (NOA) of the joint SAE/PPA/FEIS will be
published in the Federal
Register when the SAE/PPA/FEIS becomes available for
public review.
3. The SAE/PPA/FEIS will be available for public review
for 30-days before the BLM
issues a Record of
Decision (ROD). The Decision is appealable to the Interior Board
of Land
Appeals upon issuance of the ROD.
A.1.3.4
BLM’s Purpose and Need for the Proposed action
NEPA guidance published by the Council on Environmental
Quality (CEQ) states that
environmental impact
statements’ Purpose and Need section “shall briefly specify the
underlying purpose and
need to which the agency is responding in proposing the
alternatives including
the proposed action” (40 CFR §1502.13). The following discussion
sets forth the
purpose of, and need for, the project as required under NEPA.
Solar Millennium, LLC, has submitted an amended
application to apply for a ROW
authorization to
construct and operate a parabolic trough, solar thermal, generating
facility with a
capacity of 250 megawatts. The project would connect to the existing
Southern California Edison 230-kilovolt (kV)
Inyokern/Kramer Junction transmission
line. About a
mile and half long portion of this 230 kV transmission line and about a mile
and a half long
portion of a 115 kV line would be realigned to avoid the project area.
The amended application requests an approximately
3,995-acre ROW that would
contain two solar
fields, a power block, construction areas, a dry-cooling tower, steel
transmission towers with
associated transmission lines, access roads, three covered
water tanks, an
underground water pipeline, a water treatment facility, an electrical
switchyard, a land
treatment unit for bioremediation of any soil that may be
contaminated by heat
transfer fluid, an office, a warehouse, a parking lot, and facility
perimeter fencing.
The application is for a project that would be located approximately
five miles
southwest of the city of Ridgecrest in Kern County, California.
The BLM’s purpose and need is to respond to Solar
Millennium, LLC’s application will
be consistent
under FLPMA for a ROW grant to construct, operate and decommission a
solar generation
facility and associated infrastructure in compliance with FLPMA, BLM
ROW regulations, and other
applicable federal laws. BLM’s review of Solar Millennium,
LLC’s application is also consistent with the following
laws and directives pertaining to
renewable energy
resources:
• Section 211 of the Energy Policy Act
of 2005, enacted in August 2005 states, “It is
the sense of
Congress that the Secretary of the Interior should, before the end of the
10-year period beginning on the date of enactment of this
Act [August 8, 2005] seek
to have approved
non-hydropower renewable energy projects located on the public
lands with a
generation capacity of at least 10,0000 megawatts of
electricity.”Instruction
Memorandum 2007-097, dated April 4, 2007, Solar Energy
Development Policy establishes BLM policy to ensure the
timely and efficient
processing of energy
ROWs for solar power on the public lands.
• Secretarial Order 3283 Enhancing
Renewable Energy Development on the Public
Lands signed January 16, 2009. This order facilitates the
Department of the
Interior’s efforts to achieve the goals established in
Sec. 211 of the Energy Policy
Act of 2005.
• Secretarial Order 3285 Renewable
Energy Development by the Department of the
Interior, signed March 11, 2009. The order establishes
the development of
renewable energy as a
priority for the Department of the Interior and establishes a
Departmental Task Force on Energy and
Climate Change.
The decision BLM makes is whether or not to grant a ROW
and if so, under what terms
and conditions,
and whether to amend the CDCA land use plan. The SA/DPA/DEIS will
be used to
analyze the impacts of these decisions.
Modifying the existing route network is a part of the
purpose and need for this project.
The purpose and need for this project also includes
compliance with 43 CFR 8342.1
which establishes
criteria to consider when making route designations. The
designations should be
based on the protection of the resources of the public lands,
promotion of the
safety of the users of the public land, and to minimize the conflicts
among the various
users of the public lands. They also must be in accordance with the
following criteria:
• Areas and trails shall be located to
minimize the damage to soil, watershed,
vegetation, air, or
other resources of the public lands, and to prevent impairment of
wilderness
suitability.
• Areas and trails shall be located to
minimize harassment of wildlife or significant
disruption of wildlife
or significant disruption of wildlife habitats. Special attention
would be given to
protect endangered or threatened species and their habitats.
• Areas and trails shall be located to
minimize conflict between OHV use and other
existing or proposed
recreational uses of the same or neighboring public lands, and
to ensure the
compatibility of such uses with existing conditions in populated areas,
taking into
account noise and other factors.
• Areas and trails would not be located
in officially designated wilderness areas or
primitive areas.
Areas and trails would be located in natural areas only if the
authorized officer
determines that vehicle use in such locations would not adversely
affect their
natural, esthetic, scenic, or other values for which such areas are
established.
A.1.4
BLM STATUTORY SECTIONS
This section discusses the following topics that are
required to be addressed by
environmental impact
statements and reports by federal and/or California statutes,
regulations, or policy:
• Relationship Between
Short-Term Uses of the Environment and the Maintenance
and
• Enhancement of Long-term Productivity
• Irreversible and Irretrievable
Commitment of Resources
• Growth-Inducing Effects of the
Proposed Action
• Energy Consumption and Conservation
A.1.4.1
RELATIONSHIP BETWEEN LOCAL SHORT-TERM USES OF
THE
ENVIRONMENT AND THE MAINTENANCE AND ENHANCEMENT
OF
LONG-TERM PRODUCTIVITY
Consideration of energy development permits on BLM
managed lands is a trade-off
between a permitted
short-term use of the desert environment in exchange for other
uses, including
conservation and habit uses that would be effective in the longer term.
In the short term, the development alternatives allow
commercial energy generation use
of desert
lands. New disturbance would occur on the development land. This use is
incompatible with
habitat conservation on the same land.
In the long term, despite these uses, the previous
establishment of a habitat
conservation area,
including tortoise DWMAs and other conservation areas, would
ensure that desert
ecosystems would be maintained and enhanced with nearly 98
percent of the 2.2
million acre WEMO planning area maintained in an undisturbed
condition.
Additionally, an acquisition program to acquire and enhance the protection
of private
lands would be established with the required mitigation.
Closure of off highway vehicle routes through the project
area, will be off-set by creation
of alternate
routes around the project area to allow appropriate access to sites visited by
the public.
These new routes would be maintained, however, thus minimizing losses of
recreation and
commercial access. This would be accomplished by the design of a
network that
provided appropriate access in a manner that avoided sensitive resource
sites. Access
would continue to be provided for a variety of activities, including
equestrian staging
areas, recreational touring, rock hounding, mineral exploration, and
other legitimate
uses.
At the end of the term of the right of way, the land
would be reclaimed and returned to
its prior
condition and use, returning to long term productivity.
A.1.4.2
IRREVERSIBLE AND IRRETRIEVABLE COMMITMENT
OF
RESOURCES
Authorized take of habitat would result in the permanent
loss of wildlife and plant
habitat. Once new
ground disturbance occurs, the natural habitat eliminated by this
would no longer
be available to sensitive wildlife and plant species. This could include
desert tortoise
habitat. Direct take of individuals could also occur. Given the large scale
of the conservation
areas on other BLM managed lands, these disturbances are not
likely to threaten
the survival and recovery of sensitive species. Designation of
conservation areas and
previous closure of routes within those areas enhanced
ecosystem
conservation for the land within the West Mojave Plan.
All undertakings that involve ground disturbing
activities would require site-specific
cultural analysis
that may include surveys, recording of historic and prehistoric sites,
and
determinations of eligibility of sites to the National Register of Historic
Places.
Potential impacts to Native American values would be
analyzed. Mitigation measures
would be
identified and implemented if necessary. Avoidance of impacts to cultural
resources is the
preferred mitigation measure, but is not always possible or feasible. A
decision to mitigate
impacts to cultural resources by data recovery, instead of avoidance
and consequent
removal of cultural resources from the area constitutes a residual
impact to the
site. Sites would rarely, if ever, be completely excavated. Mitigation by
data recovery
results in a steady loss of archaeological sites, and reduces opportunities
for
interpretation in their natural context.
Parts of allotments no longer available for grazing use
would be lost for the reasonably
foreseeable future. The
amount of land removed from the allotment would not result in a
loss of
livestock production.
In processing the application for this renewable energy
project, BLM has made no
irreversible or
irretrievable commitment of resources.
A.1.4.3
GROWTH-INDUCING EFFECTS OF THE PROPOSED
ACTION
Population growth in the West Mojave is projected to
range between 1.59% and 2.21%
per year for
the 30-year term of the project. Adoption of streamlined procedures for
complying with the
California and federal endangered species acts increases the
likelihood that growth
rates will approximate the latter figure. This is based upon the
assumption that
applicants for discretionary development permits will have a higher
incentive to pursue
high desert projects due to the reduction and/or elimination of costs
associated with
obtaining those permits, and (more significantly) the elimination of
delays currently
inherent in the permit approval process. This growth would be focused
in the
vicinity of currently urbanized areas, including incorporated cities, rather
than in
more remote
desert regions.
This individual project is not expected to have a
significant growth-inducing effect on the
development of
BLM-administered public lands. As more energy development projects
are authorized
the State of California and the United States will be closer to meeting
their renewable
energy goals and thus reducing the demand for future projects.
A.1.4.4
ENERGY CONSUMPTION AND CONSERVATION
Any development project would result in a direct change
to the regional level of energy
development and a
minimal change to the regional level of energy conservation and
consumption.
A.1.5
U.S. DEPARTMENT OF ENERGY (DOE), LOAN GUARANTEE
PROGRAM
(LGP) OFFICE’S PURPOSE AND NEED STATEMENT
Solar Millennium has also applied to the United States
(US) Department of Energy
(DOE) for a loan guarantee pursuant to
Title XVII of the EPAct. Title XVII
of EPAct
authorizes the United
States Secretary of Energy to make loan guarantees for a variety
of types of
projects, including those that "avoid, reduce, or sequester air pollutants
or
anthropogenic emissions
of greenhouse gases, and employ new or significantly
improved
technologies as compared to commercial technologies in service in the United
States at the time the guarantee is issued." The two
principal goals of the loan
guarantee program are
to encourage commercial use in the United States of new or
significantly improved
energy-related technologies and to achieve substantial
environmental benefits.
The purpose and need for action by DOE is to comply with their
mandate under EPAct by selecting eligible projects that meet the goals of
the Act.
Should DOE enter into negotiation of a possible loan
guarantee with the applicant, DOE
would become a
cooperating agency in developing the FEIS. The need includes
consideration for this or
other funding available through the DOE. Should DOE accept
the application
as suitable for this funding, DOE may adopt this EIS, or become a
cooperating agency in
developing the FEIS. If so, this SA/FEIS may be used by DOE to
meet the NEPA
requirements in making a determination of funding.
A.1.6
U.S. FISH AND WILDLIFE SERVICE’S AUTHORITY AND
RESPONSIBILITIES
The U.S. Fish and Wildlife Service (USFWS) is charged
with protection of threatened
and endangered
species under the Federal Endangered Species Act (ESA), 16 U.S.C.
1531. ESA requires federal agencies to consult with the
USFWS or the National
Oceanic and Atmospheric Administration (NOAA) when a
federal action is likely to
adversely affect
listed species or critical habitat. Consultation is initiated by the lead
federal agency
(BLM) through the preparation and submission a Biological Assessment
(BA) to USFWS/NOAA which describes the proposed project,
its effects on the
specie(s) and its
habitat, and related avoidance and minimization measures.
Upon receipt of the BA, the USFWS/NOAA will begin formal
consultation with the BLM
to discuss the
proposed action. Following consultation, the USFWS/NOAA will then
issue a
Biological Opinion (BO). The BO may find the BLM’s proposed action will result
in “jeopardy”
to the listed species, as a whole. If so then the proposed action cannot be
taken.
Alternatively, if the USFWS/NOAA concludes the proposed action will not result
in
"jeopardy” to the listed species, as a whole, then the BO will authorize
the “incidental
take” of the
listed species1, and contain
specific avoidance and minimization measures
which must be
implemented if the proposed action is approved by the BLM. The BO
must be obtained
from the USFWS and considered by the BLM, before the BLM issues
a Record of Decision.
A.1.7
KERN COUNTY AIR POLLUTION CONTROL DISTRICT’S
AUTHORITY
AND RESPONSIBILITIES
The project site is located in the Mojave Desert Air
Basin2 and is under
the jurisdiction
of the Kern
County Air Pollution Control District (KCAPCD). Based upon the authorities
in 40 Code of
Federal Regulations (CFR) Part 52 and 40 CFR Part 60, the District is
responsible for issuing
the federal New Source Review (NSR) permit and has been
delegated enforcement
of the applicable New Source Performance Standard (Subpart
IIII).
A.1.8
CALIFORNIA DEPARTMENT OF TRANSPORTATION
(CALTRANS)
Caltrans has jurisdiction over encroachments to its
transportation facilities and related
easements and
rights-of way. Regarding the proposed RSPP, CalTrans
has authority to
consider granting an
encroachment permit for the RSPP to cross under US Route 395
with a water
line, and also granting a right-of-way and related encroachment permit for a
potential new access
from US Route 395 to the project site.
1 The BO would not authorize take of listed plant species.
For purposes of this document the BO
would potentially authorize the incidental take of the Desert
Tortoise.
2 The Mojave Desert Air Basin lies inland east of the San
Joaquin Valley Air Basin to the west and
north and east of the South Coast Air Basin. The desert
portions of Kern, San Bernardino, Riverside, and
Los Angeles counties
are within its boundaries.
A.1.9
KERN COUNTY, CALIFORNIA
The county of Kern has jurisdiction to issue building
permits to the RSPP. Building
permits issued by
the county are considered ministerial, in nature. The county also has
jurisdiction to issue
discretionary approvals for any easements, rights-of-way and or
encroachment permits
where county facilities are concerned.
A.2
ORGANIZATION OF THE STAFF ASSESSMENT/ DRAFT PLAN
AMENDMENT/DRAFT
ENVIRONMENTAL IMPACT STATEMENT
(SA/DPA/DEIS)
The SA/DPA/DEIS contains an Executive Summary,
Introduction, Project Description,
and Project
Alternatives. The environmental, engineering, and public health and safety
analysis of the
proposed project is contained in a discussion of 20 technical areas. Each
technical area is
addressed in a separate chapter. These chapters are followed by a
discussion of facility
closure, project construction and operation compliance monitoring
plans, and a list
of CEC and BLM staff that assisted in preparing and reviewing this
report.
Each of the 20 technical area assessments includes a
discussion of:
• Laws, ordinances, regulations, and
standards (LORS);
• The regional and site-specific
setting;
• Project specific and cumulative
impacts;
• Mitigation measures;
• Closure requirements;
• Conclusions and recommendations; and
• Conditions of certification for both construction and operation (if applicable).